Engineering of repair and restoration works at the dam of the Sugovushan reservoir

Published

23/07/2021

Our company carries out the design work on repair and restoration in the dam of the water reservoir Sokovushan. 

The projects included:

  • repair and restoration of all equipment of the item;
  • mechanical equipment upgrade;
  • power supply;
  • re-launch of the item in general.

The project of restoration works include the mainline canal with total length 5.2 km and other facilities on it. As part of the reconstruction work, the automatic control system of the tape devices was designed. Therefore, the construction of new administrative buildings and other service and farm buildings on the territory of the dam was also included in the project work. As a result of repair and restoration works in general. water supply of 96,200 hectares of arable land will improve.